Bountiful's planned Main Street renovation would cost an estimated $8.4 million, according to retreat minutes now before the City Council.
Public Works Director Lloyd Cheney presented the block-by-block estimate at the council's Sept. 24 retreat, according to minutes included in the Nov. 10 meeting packet. The scope stretches well beyond cosmetic upgrades.
As proposed, the project would add angled parking between 300 North and 400 South, install bulb-outs at intersections without angled parking, and place two architectural archways over Main Street. Crews would also replace the culinary water system, tear out existing pavers and replace them with concrete, rebuild sidewalks, and add five streetlights per block with banner displays.
Each planter would get a power receptacle. Two to four raised planters would be added, existing planters repaired, and irrigation extended to all planters and park strips.
The project would not touch the fountain near the post office, add lighting in planters or on trees, install pedestals for public art, or create additional mid-block crossings.
City Manager Gary Hill told the council that $3.4 million in Redevelopment Agency money would cover bulb-outs, sidewalks and pedestrian sections. Water upgrades would draw from the Water Fund. Power upgrades could come from either the Power Fund or the Capital Projects Fund.
Hill said the city had been building up the Capital Projects Fund for this purpose and that funding is in place for the project.
Mayor Kate Bradshaw asked whether outside money could help. Hill said staff had looked but found few grants the project qualifies for, aside from small portions. He said staff would keep searching.
The renovation has been in the works since at least January 2026, when department heads outlined needed improvements at a council retreat. At that earlier session, Hill said the next step was developing per-block cost estimates.
At the September retreat, council members discussed extending angled parking south to 500 South, preserving space for future public art, creating a focal point at Main Street and Center Street, replacing aging trees, the number and design of the archways, and adding way finding signage.
Hill said staff would bring more detailed information to the January retreat ahead of the budgeting process.
The Nov. 10 regular session begins at 7 p.m. at City Hall, 795 South Main Street. Residents can watch online at bountifulutah.gov or attend in person. Public comment is limited to two minutes per speaker and 10 minutes total.